Site Management Policy but No Landscaping

EBOM-v4 SSp1:Site management policy
posted by  Nitesh Kumar J  on 

I'm looking for some guidance regarding Site management policy. There is no scope of landscaping or soil in the existing site, then how do we attempt this prerequisite.

1
Fri Mar 24, 2017, 11:00 pm

Datacentre Requirements

CI-2009 EAc1.3:Optimize energy performance - HVAC
posted by  Priyadarsi Das  on 

Project Description: The project is approximately 3.0 lack Sft which is G+10 floors and going for LEED CI rating.

1
Wed Feb 11, 2015, 11:34 pm

compliance for naturally ventilated spaces

NC-v4 EQp1:Minimum indoor air quality performance
posted by  Poorva Keskar  on 

Referring to the FAQs fan-assisted ventilation in naturally ventilated spaces can be considered as mechanical ventilation.

1
Thu Aug 31, 2017, 5:37 pm

New Residential Building

NC-2009 EAp2:Minimum energy performance
posted by  SSN Energy Model  on 

Hi, We have completed the Energy Model for New Residential Building which will be located in India.

1
Thu Jun 2, 2016, 3:43 pm

Energy Submetering

EBOM-v4 EAc5:Advanced energy metering
posted by  VISHESH AGARWAL  on 

I am working on EB Project in LEED V4. In V4 the advance sub-metering is required 1. Chilled water System: Chiller and Chilled water pumps 2.

1
Wed Oct 5, 2016, 9:28 pm

Core and Shell - Retail

CS-2009 EAp2:Minimum energy performance
posted by  Rathnashree Bharadwaj  on 

We are working on a retail mall where each tenant retail space is provided with a chilled water tap off.

1
Thu Feb 2, 2017, 3:32 pm

Can a Retail CI Project achieve Water Cr if it has no Rest rooms

Retail-CI-v2009 WEc1:Water use reduction
posted by  Aswin M  on 

Can a Retail CI 2009 (restaurant) project achieve Water use reduction credit, if there is no Rest room in the (Retail CI) project scope.

1
Sat Aug 26, 2017, 11:50 pm

HVAC modelling for Tenant Occupied Spaces

CS-2009 EAp2:Minimum energy performance
posted by  Saumendra Aggrawal  on 

I am working on a project, which is going for LEED C&S. The project has tenant occupied space, which has designed HVAC system for it.

1
Sun Jun 19, 2016, 8:52 pm

Ventilation design-worst case conditions

CI-2009 IEQp1:Minimum indoor air quality performance
posted by  S Nagarajan  on 

How to provide a narrative to explain how the worst-case condition was determined considering the total design airflow rate at the condition analyzed

1
Fri Nov 19, 2021, 6:15 pm

WE Credit 4.2: Cooling Tower Water Management- non potable

EBOM-2009 WEc4:Cooling tower water management
posted by  satheesh M  on 

The project’s cooling requirement is being met by both chiller plant inside the project boundary as well as the chiller plant in the Building Owned DES.

1
Tue Dec 1, 2015, 4:07 pm