Paired bus route service

NC-v4 LTc5:Access to quality transit
posted by  Patrice McVeigh  on 

Hi, Is it necessary for both stops to be within 400m of the site in order to satisfy the paired route requirements?

1
Thu May 5, 2016, 10:56 pm

Smoking Areas - Beside a Storage Room

NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) control
posted by  Patrice McVeigh  on 

Hi All, We are building a NC Campus Project that has a non smoking policy except in one designated outside area.

1
Thu Oct 29, 2015, 12:16 pm

Contaminated soil found during excavation.

CS-2009 SSc3:Brownfield redevelopment
posted by  Martin Meehan  on 

The project involved the demolition of a existing building that had asbestos present on it.

1
Mon Feb 8, 2016, 5:28 pm

Ireland Climate Zone

CS-v4 EAp2:Minimum energy performance
posted by  James Duggan  on 

Hi all, Is Ireland Climate Zone 5A or 5C?

1
Thu Jul 20, 2017, 2:06 pm

Calculator Points clarification

Pilot-Credits MRpc102:Legal Wood
posted by  Patrice McVeigh  on 

Can you clarify the number of points available for this ACP? I believe it is 1 but if in the Validation Tap all statements for the point allocations are 'True' then the figure comes to 2.

0

Enhanced Commissioning - Final Upload

CS-v4 EAp1:Fundamental commissioning and verification
posted by  John Fingleton  on 

Hello, We are aiming to achieve all 6 credits under enhanced commissioning and we are aiming to submit the construction stage documentation upon completion of the project.

1
Thu Jan 19, 2017, 10:04 pm

Ireland Climate Zone

NC-v4 EAp2:Minimum energy performance
posted by  James Duggan  on 

Hi all, Could anyone clarify if Ireland is in climate zone 5A or 5C? Thanks in advance

1
Thu Jul 20, 2017, 2:08 pm

Eurovent Certification

General forums
posted by  Shane Geraghty  on 

Hi, I was wondering if anyone could direct me to information regarding AHU Eurovent certification requirements. Thank You

0

Paints or sealants applied before building is sealed

CS-2009 IEQc4.1:Low-emitting materials - adhesives and sealants
posted by  Patrice McVeigh  on 

Hi, If paints /sealants /adhesives are being applied on site but before the building has been enclosed do they still need to comply with the associated VOC limits?

1
Fri Apr 22, 2016, 9:42 pm

Building Envelope Air infiltration

CS-v4 EAp2:Minimum energy performance
posted by  Patrice McVeigh  on 

Hi All, I am trying to establish if a project can take benefit in the energy model for an improved air infiltration rate for the building envelope over the baseline model.

1
Mon Jan 16, 2017, 8:08 pm