Non-occupied Garage - Flush required?

NC-v4 EQc4:Indoor air quality assessment
posted by  Leanne Conrad  on 

If we have a separaetly HVAC served storage garage that is quite large and mimininally heated, does this area have to be included in the whole building flush and maintain the higher than normal tem

5
Owner/Architect
Marquis Architecture
LEEDuser Premium Member
7 thumbs up
Wed Jun 14, 2023, 6:57 pm

Advanced Metering NC Space Exemptions

NC-v4 EAc3:Advanced energy metering
posted by  Alexandra Markus  on 

I'm working on a recreation center project that includes a daycare. The daycare space will not be fit-out as part of the project.

3
Fri Jun 2, 2023, 5:32 pm
1
Fri Jul 14, 2023, 5:52 pm

No smoking signage without words

NC-v4 EQp2:Environmental tobacco smoke control
posted by  Heather Belsey  on 

I'm working on a healthcare project where the client is planning on using just the no smoking symbol on the door with no words or 'language' attached.  Just the cigarette crossed out - Is this

2
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Mon Apr 17, 2023, 6:30 pm
2
Default Avatar
Societe quebecoise des infrastructures
LEEDuser Premium Member
0 thumbs up
Fri Feb 24, 2023, 8:25 pm

Greenhouse - SRI Value

NC-v4 SSc5:Heat island reduction
posted by  Irene Chung  on 

Can a greenhouse be excluded when doing credit calculation? If not, is there a default SRI that we can use for greenhouse roofs?

2
Default Avatar
Senior Project Engineer
LEEDuser Basic Member
3 thumbs up
Fri Feb 17, 2023, 5:47 pm

Biophilic design plan

Pilot-Credits EQpc123:Designing with Nature, Biophilic Design for the Indoor Environment
posted by  Priscillia Champagne  on 

I understand that the final result must be that the project implements five distinct design strategies.

3
Mon Feb 13, 2023, 9:44 pm
4
Thu Feb 9, 2023, 5:39 am

BeCx - Ongoing commissioning plan

NC-v4.1 EAc1:Enhanced Commissioning
posted by  Manuelle Croft  on 

The commissioning authority must complete Enhance Cx tasks for the building(s)'s thermal envelope. An ongoing commissioning plan must be developped. 

0
4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Fri Feb 3, 2023, 2:20 pm