NC-2009 IEQc8.1:Daylight and views - daylightposted by Claire DeCamp on
We have a project that is going to use a combined approach due to overhangs and the prescriptive calcs not providing enough SF. I have casually measured the spaces and we exceed 20fc.
Toilet Building meet MPR?
NC-v4 MPR3:Must comply with project size requirementsposted by Harry Flamm on
Does a stand-alone one-story building, of 1,600 sf, that contains just public toilets and sinks in a park setting, and no full-time occupancy, meet minimum program requirements for LEED v4 New Cons
Ice Makers on LEED 2009 for Retail NC
Retail-NC-v2009 WEc3:Water use reductionposted by Nic Millard on
Are ice makers included in the WE 3 calculations since its Retail NC, we thought they were excluded for NC all together, but were not sure if this only applied to NC schools and core and shell.
Reuse roof joists But not roof deck
NC-2009 MRc1.1:Building reuse - maintain existing walls, floors and roofposted by C. Anne Brockelman on
I am working on a renovation project of a courthouse. We will be reusing the roof joists but will remove all the existing roof deck.
Submetering dashboard
CI-2009 EAc3:Measurement and verificationposted by Leticia SooHoo on
Hello, we are doing a LEED CI project for a large tenant occupying multiple floors. We will pursue Case 1 (less than 75% of area) - submetering.
Exemplary Performance
Schools-2009 EAc6:Green powerposted by Kevin Taterus on
LFS 2009 rating system - Our Owner on the project received a quote from a renewable energy provider that stated we could get three points total if we purchased 100% of the energy from renewable sou
43" partitions block views and negate compliance?
EBOM-2009 IEQc2.4:Daylight and viewsposted by Vanessa Seibert on
I see that there was some conversation on the views credit back in 2011.
"Material Value" in LEED credit calculation
posted by Nasim Daryaee on
Hi every one, I have a general question regards definition of " Material Value" .ie, my structure steel value in the manufacture is 200K and the cost I paid to my sub after fabrication ...
Certification agency meeting the ISO Guidelines
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Stephanie Graham on
Under the requirements of qualifying certification agencies, it reads, "The certification organization follows guidelines for environmental claims and third-party oversight, including ISO/IEC Guide
What is the baseline assumption for this credit?
CI-v4 IPc1:Integrative processposted by Betty Liu on
Hi All, We are designing a CI v4 office space in an existing high-rise building.