Separate CxA's for Fundamental and Enhanced Cx?

NC-2009 EAc3:Enhanced commissioning
posted by  Timothy Casper  on 

In a traditional design-bid-build project, does the CxA need to be responsible for both fundamental and enhanced Cx? Or can these credits be split between two CxA's?

8
Default Avatar
Tetra Tech
LEEDuser Basic Member
3 thumbs up
Thu Aug 6, 2015, 4:06 pm

Residential high rise with school at the base

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Ilana Judah  on 

We are designing a high-rise residential tower with a school and retail area at the base. There is some entry and service space serving the residential tower on the cellar and ground floor levels.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Wed Aug 5, 2015, 2:32 pm

Commissioning Documents

NC-2009 EAp1:Fundamental commissioning of building energy systems
posted by  Heather Anderson  on 

What documents are necessary to complete EA Prerequisite 1? So far, I have: 1. Fundamental Commissioning of the Building Energy System (Found on the USGBC website) 2.

4
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Mon Aug 3, 2015, 7:25 am

Calculator from USGBC

EBOM-v4 EQc8:Green cleaning - equipment
posted by  Michelle Raigosa  on 

Anyone else running into a problem with the calculator provided by the USGBC?

4
Fri Jul 31, 2015, 8:30 pm

How are individual guestroom VTACs calculated?

NC-v4 EAc3:Advanced energy metering
posted by  Karen Heet  on 

Howdy! We're working on a hospitality project and are wondering if all of the guest room VTACs are combined or counted individually for this credit? Any advice is much appreciated. Thanks!

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Thu Jul 30, 2015, 9:39 pm

Title 24

NC-2009 EAp2:Minimum energy performance
posted by  Gaston Viau  on 

Hi there My building has full T24 certification. I take it this will be satisfactory to achieve this Prereq? Thanks

9
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Wed Jul 29, 2015, 10:01 pm

fuel source

CS-2009 EAc5.1:Measurement and verification - base building
posted by  Matthew VanSweden  on 

Our project is a three story Professional Office Building addition to an adjacent hospital.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Tue Jul 28, 2015, 5:15 pm

Existing Central Plant and New building

NC-2009 EAp2:Minimum energy performance
posted by  Mital Patel  on 

We have a new building that is served by the existing central plant.

2
Default Avatar
Energy Modeler
KJWW Engineering
LEEDuser Basic Member
3 thumbs up
Fri Jul 24, 2015, 3:15 pm

TAB Report and Calculations

EBOM-2009 EAp1:Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by  Tom Liebel  on 

We have just received a request for additional clarification during our final review of our LEED-EBOM 2009 submission, asking us to confirm the date of our TAB report, and pointing us to the the Ca

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Mon Jul 20, 2015, 9:00 pm

LEED Online v4 for Multiple Buildings on a Campus

LEED Guidance for Campuses and Multiple Buildings
posted by  Deborah Lucking  on 

LEED Online v4 was a surprise in more ways than one. The individual projects are now certified under the Master Site, which is certified under the Campus (the old "block"). All well and good.

5
Director of Sustainability
Fentress Architects
LEEDuser Expert
224 thumbs up
Mon Jul 20, 2015, 6:32 pm