Commingled waste sorted off-site
CI-v4 MRp1:Storage and collection of recyclablesposted by Pooja Sannamani on
Would be acceptable to have 1 bin for commingled recyclable waste (+ 1 bin for e-waste + 1 bin for batteries) and a waste contract that confirmes that commingled recyclable waste is sorted int
Green Power contract engagement question
NC-v4 EAc7:Green power and carbon offsetsposted by Norbert Harmathy on
Hello,
We want to apply for the Green Power and Carbon Offset credits under LEED v4 BD+C New Construction & Major renovation project.
Table 7.8 DHW performance requirements for electric instantaneous water heater
NC-v4 EAc2:Optimize energy performanceposted by Kent B on
I see there is "Gas Instantaneous Water Heaters" in Table 7.8, but there is not an "Electric Instantaneous Water Heater" in the table. Is the "Electric Water Heaters" term meant to be generic
Piping Insulation
NC-v4 EQc2:Low-emitting materialsposted by Megan White on
For new construction projects, the Ref Guide excludes insulation around HVAC ducts from the IEQc2 requirements (p.668).
Demand Response for Residential buildings
NC-v4 EAc4:Demand responseposted by Amanda Cunningham on
Has anyone pursued this credit for a multifamily building? I'm assuming the automated demand response would only apply to common areas under the building management's control.
Should archaeological works, taking place before construction start, be included in ESC Plan?
NC-v4 SSp1:Construction activity pollution preventionposted by Agata Mozer on
Dear All,
Can you round percentages on indoor water use reduction?
NC-v4 WEc2:Indoor water use reductionposted by Nate Shroyer on
Hi! Our project is currently meeting 49.95% reduction on indoor water use. Does anyone have any experience about whether it is possible to round this up to 50% for the maximum of 6 poin
EA Credit: Enhanced Commissioning
CI-v4 EAc1:Enhanced commissioningposted by Lawrence Rennell on
What level of testing is actually required for LEED V4 enhanced commissioning envelope testing?
Interior blinds for energy performance
NC-v4 EAc2:Optimize energy performanceposted by Julio Fernandez Amodia on
Hi there,
Wastewater from Concrete Washout facility
NC-v4 SSp1:Construction activity pollution preventionposted by Osman Faroq on
Dear All,