Demand Response Plan - who creates the plan?

NC-v4 EAc4:Demand response
posted by  Deborah Lucking  on 

We have a mechanical engineer, an electrical engineer, a commissioning agent, and an energy modeler.  Looking for advice on who is the appropriate author of such a plan.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Fri Aug 16, 2019, 4:40 pm

exceptions for farmland?

NC-v4 LTc2:Sensitive land protection
posted by  Erica Downs  on 

We have an infill site on a university campus.  Unfortunately, this particular plot of land was previously undeveloped.  When checking the soils survey site, a portion of the site comes u

2
Director of Sustainability
NORR
LEEDuser Expert
7 thumbs up
Thu Aug 15, 2019, 6:02 pm

Permanently installed products definition.

CI-v4 MRc5:Building product disclosure and optimization - material ingredients
posted by  shashank gangil  on 

For MR credits, what exactly contributed as permanently installed product? Does AC ducts and insulation counted here?

2
Architect
CRSA
LEEDuser Basic Member
1 thumbs up
Thu Aug 15, 2019, 3:03 am

Fixtures within Lab Facility - Applicable

NC-v4 WEp2:Indoor water use reduction
posted by  RDK E&S  on 

Hello, 

I'm working on a lab / processing facility aiming for LEED v4 NC certification.

4
Default Avatar
Energy Engineer / Sustainability Specialist
NV5
LEEDuser Basic Member
15 thumbs up
Thu Aug 15, 2019, 1:21 am

SSpc41 Walkable Project Site

NC-v4 INc1:Innovation
posted by  Helene Lefkowitz  on 

Our project team pursued this pilot credit and found it to be very achievable for projects in urban settings.

2
Wed Aug 14, 2019, 9:04 pm

5 Regional Priority Credits

NC-v4 RPc1:Regional priority
posted by  Nathan Gauthier  on 

I was checking the RP credits for LEED v4 NC in Cambridge today and there are only 5 listed (not 6). Boston is the same way.

3
Director of FM Integration and Sustainability
Shawmut Design and Construction
LEEDuser Basic Member
21 thumbs up
Wed Aug 14, 2019, 8:59 pm

PV Lease Agreement Clarification

NC-v4 EAc5:Renewable energy production
posted by  Jeff Ross-Bain, PE, LEED Fellow, WELL AP  on 

Our project intends to provide land, under a min. 10-year lease, to the local power provider who will install a min. 1MW PV system.

1
Thu Aug 15, 2019, 6:46 pm

Exemplary Threshold

NC-v4 LTc5:Access to quality transit
posted by  Jane Bills  on 

I have a Core & Shell project with the following:

RAIL:

249 Weekday          117 Weekend

BUS:

1
Thu Aug 22, 2019, 5:23 pm

Default values used in calculator

NC-v4 EAc6:Enhanced refrigerant management
posted by  RDK E&S  on 

Are refrigerant GWPr and equipment life (years) typically shown on cutsheets, or are default values sufficient for this credit?

1
Wed Aug 14, 2019, 8:17 pm

Compliance to ASHRAE 90.1-2010 - Dimming Lights

CS-v4 EAp2:Minimum energy performance
posted by  Summer   on 

I'm working on an office project located at the top of a 3-level podium and has a 4-level basement parking.

1