Thu Feb 8, 2018, 3:04 pm

Minimum 18% energy saving after April 2016 - Scoring

NC-2009 EAc1:Optimize energy performance
posted by  Eric Claycamp  on 

My project will likely reach 20% to 23% Energy Savings. Does this mean I can only score the points after I meet the minimum? In other words is a 20 percent reduction only one credit point?

3
Thu Dec 28, 2017, 4:02 pm

Energy modeling- DOAS units with reactivation air

NC-2009 EAc1:Optimize energy performance
posted by  Matt Hollenbeck  on 

I have an HVAC system that will use a DOAS unit to supply neutral temperature air in a humid climate (climate zone 2).  The proposed DOAS unit utilizes a dessicant wheel with reactivation

3
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Sat Dec 9, 2017, 7:31 pm

Office Building with Data Center

NC-2009 EAc1:Optimize energy performance
posted by  Lise Dannesboe  on 

I have a possible case with a office building that also contains a large Data Center.

5
Delta Electronics
LEEDuser Basic Member
0 thumbs up
Mon Nov 27, 2017, 2:36 pm

Energy Saving from Process Boiler

NC-2009 EAc1:Optimize energy performance
posted by  sompoche sirichote  on 

Our project is an existing manufacturing project and we have 1 existing steam boiler and will install 1 new.

3
Thu Oct 12, 2017, 9:51 am

Lift Energy assessment in LEED

NC-2009 EAc1:Optimize energy performance
posted by  Edwin Wealend  on 

Hi Is lift energy included as a process load as part of the 25% minimum requirement for process loads? If so are there any references or guidance on how to estimate its energy consumption.

1
Wed Feb 9, 2011, 2:08 pm

Questions about High-rise residential LEED Energy Modeling

NC-2009 EAc1:Optimize energy performance
posted by  Tommy Xing  on 

Hi I’m working on a High-rise residential LEED energy modeling project now. I have a question regarding the lighting.

0

LED Lamps in Fixtures Designed for Other Lamps

NC-2009 EAc1:Optimize energy performance
posted by  Pat Thomas  on 

We are planning to use fixtures designed for use with MR-16 or incandescent lamp but will be installing LED lamps.

1
Thu Feb 7, 2013, 1:54 pm

Building Envelope Requirements for Continuous Insulation

NC-2009 EAc1:Optimize energy performance
posted by  Myra Villalobos  on 

We have a project that has structural masonry walls, and interior steel studs. Appendix G requires 7.5 c.i. for our walls, so I have two questions: 1.

1
Tue Jul 19, 2011, 7:27 pm

Process Load or Regulated Load

NC-2009 EAc1:Optimize energy performance
posted by  Erin Nuckols  on 

In the case of a museum, is the humidification of a structure considered process load or regulated load?