Forum quick links
Baseline Heating Source for Zone Served by Both Purchased Heat and Gas Radiant Heaters
Warehouses-NC-v4 EAp2:Minimum energy performanceposted by Aleksandra Gornisiewicz on
We have an industrial hall where a single thermal zone is heated by two separate systems:
Unknown Glazing Performance
CI-v4 EQc7:Daylightposted by Cory Duggin on
We are working on a CI project where the existing glazing performance is unknown. Is there a conservative, default value the GBCI will accept for use in the daylight simulations?
Integrative Analysis of Building Materials - LEED v4 CS
Pilot-Credits MRpc103:Integrative Analysis of Building Materialsposted by Jessica Glorius-Dangelo on
I found the information relatively easy to find with the documentation provided by the product manufacturers.
For proposed case with spot cooling only, how to model baseline and satisfy unmet for both propsoed and baseline
NC-v4 EAp2:Minimum energy performanceposted by Akhil Sumer on
Hi,
A proposed case with spot cooling in kitchen/food prep area is mechanically ventilated aswell. The spot cooling is served by PAHU units connected to ODU.
Perimeter Area Calculation
Healthcare-v4.1 EQc7:Daylightposted by Selin Guner on
Hi
On a LEED BD+C: Healthcare project, some perimeter rooms are deeper than 15 ft, and the space continues as a single, undivided room (for example, 30 ft deep).
Baseline HVAC system datacenter
Data-Centers-NC-v4 EA403:Minimum Energy Performance (2024 Update)posted by Boris Jonjic on
Hi all,
I've got a question regarding the baseline HVAC system for a datacenter project. Modeling in DesignBuilder and using ASHRAE 90.1 2010.
Baseline pressure drop adjustments
NC-v4 EAp2:Minimum energy performanceposted by Boris Jonjic on
Hi all,
I've got a question about calculating the pressure drop adjustments for a baseline building. I'm using LEED v4, ASHRAE 90.1 2010.
Documentation Crosswalks
Pilot-Credits MRpc132:Procurement of Low Carbon Construction Materialsposted by Angi Rivera on
Hi, All - We just completed our documentation of the pilot credit, and it was incredibly straightforward for our project.
Outdoor Airflow Measurements and Potential Corrective Action
EBOM-v4.1 EQp1:Minimum Indoor Air Qualityposted by CT G on
We are currently working on a project in which, during the outdoor airflow measurements, we identified that the ventilation fans were delivering significantly lower outdoor airflow rates than requi
Implementation of Water Leak Detection and Monitoring Pilot
NC-v4 INc1:Innovationposted by Lorena Montenegro on
It is not clear what the action plan must have in order to comply with the requirements of the credit.