Forum quick links
Design for Indoor Air Quality and Infection Control Documentation
Pilot-Credits INpc155:Design for Indoor Air Quality and Infection Controlposted by Katherine Tich on
Anyone with experience documenting this credit - did you submit with the design credits or with the construction credits?
Is this SSpc158 Pilot credit available for international projects?
Pilot-Credits SSpc158:Onsite Carbon Sequestration Through Plantingsposted by Andres Schwarz on
I have noticed that the calculator starts asking for the project location, but it only addresses US states (https://planting.itreetools.org/app/location/).
All-Gender Restrooms
Pilot-Credits WEpc147:All-Gender Restroomsposted by Maggie Ma on
The University of Toronto has implemented the All‑Gender Restrooms pilot credit as part of our broader commitment to equity, diversity, and inclusion.
50% of Receptable Controls to meet the Prerequisite
NC-v4 EAp2:Minimum energy performanceposted by Kritika Kharbanda on
We are working on a project where it was missed during equipment procurement that open office furniture is required to have 50% of the receptacles controlled to meet the prerequisite under 90.1-201
Comprehensive Composting
NC-v4 INc1:Innovationposted by Alma Evans on
Hi there, I registered the project I worked on in Austin, TX - Govalle Elementary School for the comprehensive composting pilot innovation point and I want to thank AISD for providing the requ
Applicability of Rainwater Management Credit – Direct Discharge to Natural Stream
NC-v4 SSc4:Rainwater managementposted by Ahmed Alyousef on
We are seeking clarification on the applicability of the Rainwater Management credit based on our current stormwater strategy.
Use High Priority Site as Innovation
CS-v4 LTc3:High priority siteposted by Sara Johansson on
Hello, I have a CS v.2009 project and wish to use the High Priority v.4 credit as an innovation credit.
Battery room (Litium-ion)
Data-Centers-NC-v4 EQc1:Enhanced indoor air quality strategiesposted by Suksan Yongwattananun on
Our data center project has had litium-ion battery rooms which the pollution from battery can't occur in normal operation because of the litium-ion battery type.
Autocase inputs slightly different than LEED Outputs
Pilot-Credits INpc113:Informing Design Using Triple Bottom Line Analysisposted by Jill Kurtz on
We use the Autocase tool for this innovation credit and find some of the inputs they require are slightly different than how LEED outputs information.
Daylight & Views – Simulation Approach for New Construction with Phased Core & Shell (Temporary Conditions vs. Final Design)
NC-v4.1 EQc7:Daylightposted by Kate Sector on
Hi all,