Projects with no associated off-street parking
CS-v4 LTc7:Reduced parking footprintposted by Esteban Martinez on
The team has the following doubt: at the LEED guide says that the project allowable parking must be less or equal to minimum code, but then says that if the project is not associated to off-street
Campus Thermal Energy System - Multiple Buildings
NC-v4 EAp2:Minimum energy performanceposted by Senna Sabir on
Hello,
Light reflection from the facade
NC-v4 SSc6:Light pollution reductionposted by Agnieszka Rylska on
Ligting engineer asked me if he should include light reflection from the facade in the ligthing simulation for Light trespass Option 2. Could anyone confirm this?
Squat WC using manual flushing
Warehouses-NC-v4 WEp2:Indoor water use reductionposted by Iqbal Khalilullah on
Dear All,
We have 2 nos of squat toilet within the development for the security and driver room. However, the flushing system will be manual using bucket.
Gravel, Ice-Plants
NC-v4 SSc3:Open spaceposted by Michael Tsang on
Hello LEEDuser Community!
I have two questions related to calculating the 25% Vegetated Space for the Sustainable Sites Credit in LEED v4.0:
Reading 1168 for Other Architectural Sealants
NC-v4.1 EQc2:Low-Emitting Materialsposted by Joseph Snider on
Hi All - I noticed that the v4 calculator was different than the v4.1 calculator for the category of "All Other Architectural Sealants." It went from 250 g/L to 50 g/L which is a big shift, a
Compliant air-cleaning devices for ozone
NC-v4 EQp1:Minimum indoor air quality performanceposted by LEEDme Lorenzi on
We are working on a project where the ozone levels exceed the most recent three year average, so we must include air-cleaning devices for ozone.
SMart certfication vs Floorscore
NC-2009 IEQc4.3:Low-emitting materials - flooring systemsposted by Alicia Ravetto on
Will SMaRT certification for a Forbo linoleum flooring be accepted vs Floorscore certification?
WC's in expansion
NC-v4 WEp2:Indoor water use reductionposted by Ricardo Sá on
Dear All,
One of our clients is developing an expansion to an existing airport.