Forum quick links
Airflow monitor alarms
NC-v4 EQp1:Minimum indoor air quality performanceposted by Nancy Henderson on
We have several single zone RTU's that will need direct airflow monitors because the units have DCV. The contractor says the low OA alarm will be located on the units at the roof. They
Fire Station minimum parking?
NC-v4 LTc7:Reduced parking footprintposted by Erin Holdenried on
Looking for suggestions on how to determine the parking ratio for a Fire Station. There doesn't seem to be any use within the Base Ratios Table that align with a Fire Station.
DES Cooling tower
EBOM-v4 WEc3:Cooling tower water useposted by Elyse Dufrene on
Can DES cooling tower serving the project be used to demonstrate water consumption reduction for cooling tower water use credit?
Views for Medical Exam Rooms
NC-v4 EQc8:Quality viewsposted by Kyle Ritchie on
Our project is pursuing LEED v4 BD+C certification and is a University building.
Earthquake preparedness
Pilot-Credits IPpc99:Design for Enhanced Resilienceposted by Andrew Ondersma on
Our project pursued this pilot for Earthquake specific design measures.
Environmental noise impacts constantly evolving
Pilot-Credits EQpc57:Enhanced acoustical performance - exterior noise controlposted by Andrew Ondersma on
For this credit our project had a unique challenge in that many adjacent city blocks were also under construction meaning that the environmental noise impacts to our site would be constan
Preferred parking/ Charging stations allocated off - site
NC-v4 LTc8:Green vehiclesposted by on
We have a project on a university campus that will have no new parking associated with the project. However, the design team is hoping to achieve points for LTc8.
Is painted gypsum considered a hard-lid ceiling
CS-2009 IEQc5:Indoor chemical and pollutant source controlposted by Edgar Arevalo on
I am looking at the "Negatively Pressurized Rooms" section for this credit, and I noticed that separation method includes an option for hard-lid ceiling. I am curious, after looking at the fi
Jan 1, 2019 change to SCAQMD Rule 1113 and 1168
NC-v4 EQc2:Low-emitting materialsposted by Keith Robertson on
Maybe this question has been posed in another forum and I am not seeing it, but when does the new limit become applicable?
Removing "other" costs from total construction cost of project
CS-2009 MRc4:Recycled contentposted by Edgar Arevalo on
I am looking at a spreadsheet with the total construction cost for the project. I already shaved off HVAC, Electrical, Plumbing, and other equipment costs from the total (including audiovisua